We use cookies for analytics to improve your experience. Privacy Policy
Delay claims and liquidated damages (often referred to as "delay penalties" in the Gulf context) are among the most financially significant issues in GCC construction disputes. On mega-projects in the UAE, Saudi Arabia, and Qatar — where contract values regularly exceed USD 500 million and construction programmes span three to five years — the cumulative exposure to liquidated damages for delay can reach tens or hundreds of millions of dollars. Understanding the legal framework governing the enforceability and reduction of liquidated damages is essential for contractors, employers, and project financiers.
Under UAE law, liquidated damages in construction contracts are governed by the general provisions of the UAE Civil Code (Federal Law No. 5 of 1985, as amended). Article 390(1) provides that the contracting parties may fix the amount of compensation in advance by a provision in the contract or in a subsequent agreement. However, Article 390(2) grants the court a broad discretion to modify — either by increasing or decreasing — the agreed compensation amount so that it is equal to the actual loss suffered by the injured party. This judicial power to intervene in the agreed damages amount is a distinctive feature of UAE contract law (and civil law systems generally) that has no direct equivalent in English law, where the penalty/liquidated damages distinction operates differently.
In practice, UAE courts and DIAC arbitral tribunals have applied Article 390(2) to reduce contractual delay damages where the employer cannot demonstrate that the agreed rate bears a reasonable relationship to the actual loss caused by the delay. The burden of proof is nuanced: the contractor seeking a reduction must first establish that the contractual rate is excessive relative to the actual loss, and the employer must then demonstrate the loss it has actually suffered. Where the employer has not mitigated its loss, has contributed to the delay through variations or late instructions, or has taken beneficial occupation of the works before formal completion, tribunals have consistently reduced the contractual rate — in some cases by 50% or more.
The interaction between liquidated damages and extension-of-time (EOT) entitlements is particularly significant. Under most standard form construction contracts used in the Gulf — including FIDIC 2017 — the Contractor is entitled to an extension of time for delays caused by the Employer, force majeure events, or other specified causes. Where the Contractor establishes an entitlement to an EOT, the contract completion date is extended and liquidated damages cannot be levied for the period covered by the extension. However, the "concurrent delay" problem — where both Employer-caused and Contractor-caused delays overlap — remains one of the most contested issues in Gulf construction arbitration. UAE tribunals have adopted varying approaches to concurrent delay, with some following the English "dominant cause" analysis and others applying a proportional allocation methodology.
For contractors operating in the Gulf, the practical implications are clear. First, maintain contemporaneous delay records — daily progress reports, correspondence regarding instructions and variations, and programme updates — that can support an EOT claim and demonstrate the employer's contribution to delay. Second, ensure that contractual notice requirements for EOT claims are strictly complied with, as failure to give timely notice can forfeit the entitlement regardless of merit. Third, where liquidated damages are levied, assess whether the contractual rate can be challenged under Article 390(2) — a challenge that requires evidence of the employer's actual loss (or lack thereof). GSDA Legal Consultants' construction team advises contractors and employers on delay analysis, EOT claims, and the enforcement and reduction of liquidated damages across all GCC jurisdictions.
Our team is ready to assist you with expert counsel tailored to your situation.